Skip to main content
  • City of PORTSMOUTH NH
  • Department of Public Works
A A A
Department of Public Works
  • Operations Back Copy Created with Sketch.
    • Engineering
    • Geographic Information Systems
    • Parks & Greenery
    • ParkPortsmouth
    • Recycling Center & Solid Waste
    • Roads & Sidewalks
    • Stormwater
    • Transportation
    • Wastewater & Sewer
    • Water
  • Services Back Copy Created with Sketch.
    • Snowstorm Parking Info
    • Recycling Center
    • Waste Collection Schedule
    • Drinking Water Quality
    • Mosquito Control
    • Household Hazardous Waste Day
  • Resources Back Copy Created with Sketch.
    • Adopt-A-Spot
    • Billing Information
    • Catch Basins & Fire Hydrants
    • Permits & Applications
    • Portsmouth Click N' Fix
    • Post-Closure Landfill Monitoring
    • Water & Sewer Assistance Program
    • Snow Related Impacts & Notifications (CodeRED)
    • Water Efficiency Rebate Program
  • Projects Back Copy Created with Sketch.
    • Citywide Map
    • Bartlett Street
    • Capital Improvement Plan
    • Congress Street
    • Community Campus
    • Community Policing Facility
    • Edmond-Woodbury
    • Elwyn Park Sidewalks & Traffic Calming
    • Elwyn Road
    • Elwyn Road Side Path
    • Fleet Street Sewer Separation
    • Hampshire & Essex
    • Hanover Garage
    • Islington Creek
    • Lafayette Park
    • Mechanic St. Pump Station
    • Middle/Miller/Summer St
    • Pease Water
    • Pease WWTF
    • Peirce Island WWTF
    • Peirce Island Road Resiliency
    • Peirce Island Outdoor Pool
    • Peverly Hill Road
    • Rail Trail
    • Rte 1 Bypass-Coakley Intersection/Cate St. Bridge
    • Sidewalks
    • Sound Barriers
    • South Mill Pond Playground
    • Vaughan Mall
    • Woodbury Ave.
    • Other Projects
  • MapGeo
  • Contact
  • Developments
  • City of Portsmouth
  • Public Works Home
  • Congress Street Infrastructure Project

Congress Street Infrastructure Project

Subscribe

* indicates required
 
 

Utility replacement on Congress Street began the week of January 5, 2026 and is expected to extend to early June. Construction started at Vaughan Mall and is working towards Maplewood for the drainage and sewer mains. 

For the week of January 26, work is anticipated (weather permitting) to include: 1) Sewer and Drainage main installation continuing on Congress Street towards Maplewood Avenue; and 2) Temporary water service installations in the direction of Fleet Street.

Work includes the full replacement of sewer collection, water distribution, and stormwater infrastructure from Maplewood Avenue to a point approximately 100’ beyond (East) of the Fleet Street intersection. This portion of work will also include the restoration of Congress Street in the fall of 2026 beginning after Labor Day.

Like the Vaughan Mall project, the work can be disruptive to pedestrians and traffic.  Similar barricades will be used as required to aid pedestrians in the vicinity of the work zones as were used during work in the Vaughan Mall work to maintain access to businesses.  Crews will maintain at least one lane of vehicular traffic and safe sidewalk passage; however, some work days will require the temporary closure of Congress Street and/or the Fleet Street intersection during working hours in which case detour routes will be established.

The City is proceeding with this work starting this winter in an effort to limit impacts to businesses. It is expected that the major utility work and most significant impacts to businesses will be completed over the winter leaving temporary roadway and sidewalk reconstruction for the spring. Work is scheduled to take place daily, Monday through Friday but there may be brief interruptions if conditions become too severe for crews to work effectively.  

A pre-construction public information meeting for the project was held on December 9, 2025. For more information, visit the meeting presentation and the video recording.
 

Background

The work on upper Congress Street is the second part of Phase 1 of the sewer separation project of the Fleet Street Area that is being required by the City's Long Term Control Plan and Supplemental Compliance Plan. The project includes new water, sewer and drainage upgrades along with full streetscape rework and other pedestrian enhancements.

Given the scope of this larger Fleet Area project, it is being completed in phases: 

  • Phase 1, infrastructure work in the Vaughan Mall and upper Congress Street area that began September 1, 2025.
  • Phase 2, a new drain line down Maplewood Avenue to the drainage outfall at North Mill Pond and
  • Phase 3, Fleet Street from Hanover Street to Court Street.

Meetings

12.9.2025 Congress Street Public Information Meeting

12.9.2025 Congress Street Public Information Meeting

December 10, 2025

12.9.2025 Congress Street Public Information Meeting

  • City of PORTSMOUTH Home >
blue public works seal

Department of Public Works

Home Office
680 Peverly Hill Rd, Portsmouth, NH 03801
Hours

Monday – Friday 7:30 AM - 3:30 PM

Phone
(603) 427-1530
Fax
(603) 427-1539

Resources

  • Drinking Water
  • Forms & Permits
  • Click N' Fix
  • Contact
blue public works seal

© 2026 - City of Portsmouth. All Rights Reserved. | Terms of Use | Disclaimer