Skip to main content
  • City of PORTSMOUTH NH
  • Department of Public Works
A A A
Department of Public Works
  • Operations Back Copy Created with Sketch.
    • Engineering
    • Geographic Information Systems
    • Parks & Greenery
    • ParkPortsmouth
    • Recycling Center & Solid Waste
    • Roads & Sidewalks
    • Stormwater
    • Transportation
    • Wastewater & Sewer
    • Water
  • Services Back Copy Created with Sketch.
    • Snowstorm Parking Info
    • Recycling Center
    • Waste Collection Schedule
    • Drinking Water Quality
    • Mosquito Control
    • Household Hazardous Waste Day
  • Resources Back Copy Created with Sketch.
    • Adopt-A-Spot
    • Billing Information
    • Catch Basins & Fire Hydrants
    • Permits & Applications
    • Portsmouth Click N' Fix
    • Post-Closure Landfill Monitoring
    • Water & Sewer Assistance Program
    • Snow Related Impacts & Notifications (CodeRED)
    • Water Efficiency Rebate Program
  • Projects Back Copy Created with Sketch.
    • Citywide Map
    • Capital Improvement Plan
    • Bartlett Street
    • Community Campus
    • Community Policing Facility
    • Corporate Drive
    • Elwyn Park Sidewalks & Traffic Calming
    • Fleet Street Area
    • Fleet Street Sewer Separation
    • Greenleaf Sidewalks
    • Hampshire & Essex
    • Hanover Garage
    • Islington Street
    • Little Bay Road Water Main
    • Marjorie Street Pump Station
    • Maplewood Ave. Bridge
    • Mechanic St. Pump Station
    • Middle/Miller/Summer St
    • North/Union Cemetery Seawall
    • Pease Water
    • Pease WWTF
    • Peirce Island WWTF
    • Peirce Island Road Resiliency
    • Peirce Island Outdoor Pool
    • Peverly Hill Road
    • Rail Trail
    • Rte 1 Bypass-Coakley-Cottage Intersection
    • Sagamore Avenue
    • Sidewalks
    • Sound Barriers
    • South Mill Pond Playground
    • Union Street Sewer Separation
    • Willard Ave. Sewer
    • Woodbury Ave.
    • Other Projects
  • MapGeo
  • Contact
  • Developments
  • City of Portsmouth
  • Public Works Home
  • Fleet Street Area Reconstruction Project

Fleet Street Area Reconstruction Project

Project Status: December 2024

Design work and permitting continues on all portions as the project has been split into three distinct construction areas. The project areas are Upper Congress Street and Vaughan Mall, Maplewood Avenue from the railroad tracks to Hanover Street for the drainage outfall, and Fleet Street.

Project Description

The City is moving forward with a sewer separation project in the Fleet Street area (CM 20-PW-100) as it is required through the City's Long Term Control Plan and Supplemental Compliance Plan. The project includes water, sewer, drainage upgrades along with full streetscape rework and other pedestrian enhancements. Funding for this work will come from the Water and Sewer Enterprise Funds and the General Fund (property taxes). Given the scope of this project, it will need to be completed in phases. The first two construction projects will take place in 2025 both in the Vaughan Mall and the construction of a new drain line under Maplewood Avenue from Hanover Street to the North Mill Pond. 2026 will see the construction move into the Upper Congress Street area from Fleet Street to Maplewood. Finally in 2027, the project will start on Fleet Street from Hanover Street to Court Street. Downtown Aerial Utilities Underground (BI-21-PW-43) project is funded to bury the Fleet Street overhead utilities. Market Square Upgrade project (TSM-15-PW-61) is also being coordinated with this project.

Anticipated Completion 2027

Estimated Cost $11.2 million.

Funding Source/Status Bonding and Water/Sewer Fund.

Designer/Contractor: Underwood Engineers, Inc.

While the project is focused on Fleet Street from Hanover Street to Court Street, a larger area will be studied in the initial phases of engineering so that the utilities and other improvements can be properly designed. A map of the study area is shown below:

Fleet Street Project Area (not to scale)

For this map to scale, click here.

Subscribe

* indicates required

View previous campaigns.

 
 

The City conducted a survey seeking input from those in the Fleet Street Project Area (map below) regarding what they'd like to see for sidewalk and landscape improvements as part of the project. The City's contractors Underwood Engineers offered some examples of previous streetscape improvements. Among the considerations:

  • Pedestrian accommodations and seating
  • Traffic patterns & calming
  • Landscape & trees
  • Bike accommodations
  • Overhead utilities
  • Parking
  • Curbing realignments

For more information, click here.

Design drawings for Fleet Street reconstruction

For the Plan View drawings alone, click here.

Presentation to Parking & Traffic Safety Committee (January 5, 2023)
Parking & Traffic Safety Meeting Presentation November 16, 2021
Public Information Meeting Presentation May 6, 2021
Information Meeting Presentation September 9, 2020
Zachary Cronin
Zachary Cronin

Zach Cronin

Assistant City Engineer
(603) 610-7304

Fleet Street Public Meetings

11.16.2021 Parking and Traffic Safety Committee

11.16.2021 Parking and Traffic Safety Committee

December 21, 2022

11.16.2021 Parking and Traffic Safety Committee

05.06.21 Fleet Street Reconstruction Project Public Meeting

05.06.21 Fleet Street Reconstruction Project Public Meeting

May 10, 2021

11.14.20 Fleet Street Utility Coordination Public Meeting

11.14.20 Fleet Street Utility Coordination Public Meeting

November 18, 2020

09.09.20 : Fleet Street Public Information Meeting

09.09.20 : Fleet Street Public Information Meeting

September 14, 2020

Go To YouTube Playlist
  • City of PORTSMOUTH Home >
blue public works seal

Department of Public Works

Home Office
680 Peverly Hill Rd, Portsmouth, NH 03801
Hours

Monday – Friday 7:30 AM - 3:30 PM

Phone
(603) 427-1530
Fax
(603) 427-1539

Resources

  • Drinking Water
  • Forms & Permits
  • Click N' Fix
  • Contact
blue public works seal

© 2024 - City of Portsmouth. All Rights Reserved. | Terms of Use