Corporate Drive

Completed Updated July 15, 2026

Project Overview

This project is completed. 

The City of Portsmouth has a sewer improvement project that consists of the replacement of existing sewer pipes in Goosebay Drive and also in Corporate Drive from Rye Street to Goosebay Drive (see project area below). The City received bids in March 2024 and awarded the construction contract to Sargent Corporation of Stillwater, ME. This project is completed. 

Area of Impact

Project Updates

Update 2025 Feb 20, 2025

This project is completed. 

Update 2019 Jan 1, 2019
  • Work is substantially complete and the contractor has demobilized.
  • Punch list items remain to be completed. Final paving is anticipated to occur in the Spring of 2019.