Project Overview

This FY26 project is a street drainage improvement providing stormwater drainage to eliminate the pooling in Lafayette Park. Funding comes from the Water and the Sewer Enterprise Funds as well as General Funds.

Phase one will be improvements to the water, sewer and storm drainage on Monroe Street at Lafayette Park in order to separate stormwater from sanitary sewer and prevent ponding in playground. Phase two of this project, in FY28 and FY29, will fund design and construction of playground and field improvements at the park.

Project Map

Project Updates

CIP / Budget Information

 

 

Project Documents

This section includes project-related documentation for the Lafayette Park and Monroe Street Drainage Improvements project, including Capital Improvement Program (CIP) information and supporting materials.

Project FAQ

What is the Lafayette Park – Monroe Street project?

The Lafayette Park – Monroe Street project is a stormwater and utility improvement project on Monroe Street adjacent to Lafayette Park. The work focuses on improving drainage infrastructure to address water pooling and improve conditions in the park area.

Why is this project being done?

The project is intended to improve stormwater drainage and eliminate pooling that has occurred in Lafayette Park, particularly in the playground area. Upgrading the drainage system will help move stormwater away from the park more effectively.

What work is included in Phase One of the project?

Phase One includes improvements to the water, sewer, and storm drainage infrastructure on Monroe Street. The work will also separate stormwater from the sanitary sewer system, which helps improve drainage and utility system performance.

How is the project funded?

Funding for the project comes from a combination of Water and Sewer Enterprise Funds and the City’s General Fund.

Are there additional improvements planned for Lafayette Park?

Yes. Phase Two of the project, planned for FY28–FY29, will include the design and construction of improvements to the park’s playground and field areas following completion of the drainage work.