Willard Ave. Sewer

Completed Updated July 15, 2026

Project Overview

The Department of Public Works began the process of a sewer separation project in the Union Street area in the spring of 2022. Although only the Union Street area falls within the Consent Decree zone, residents in the adjacent Willard Avenue area have complained about sewer odors, so the City will address that issue by installing separate sewer and stormwater mains in this area at the same time. As part of the City’s Wastewater Master Plan and Long Term Control Plan, separating wastewater from stormwater is an ongoing responsibility under the Consent Decree agreement between the City of Portsmouth and the Environmental Protection Agency (EPA) and New Hampshire Department of Environmental Services (NHDES). The project involves the installation of three separate water mains: one for drinking water, one for wastewater and one for stormwater, along with reconstruction of the streets. The project will help reduce combined sewer overflows (CSOs) when the single pipe is flooded with stormwater in heavy rain events. 

This project included the reconstruction of the Willard Street area from Middle Street to Marston St. and includes Orchard St and Ash St.  The replacement of sidewalks, pavement, and underground utilities including new storm drains, sanitary sewers and water mains are all a part of the project. 

This project is part of the City’s continued sewer separation to reduce combined sewer overflows. 

Project Team

Designer/Contractor: CMA Engineers, Inc. Zachary Cronin, Assistant City Engineer 603-610-7304 or 603-957-8795
zmcronin@portsmouthnh.gov

Project Map

Project Updates

9/12/2026 Weed Control, Hydroseeding, and Pavement Striping Sep 12, 2026

On Friday, September 12, 2025 the contractor applied weed control horticultural vinegar -- which causes no harm to people, pets or other animals. After allowing the vinegar to do its work, the contractor will rake out the dead weeds before hydroseeding to promote grass growth. Pavement striping was also completed on September 12.

4/17/2024 Preconstruction Meeting Dec 4, 2024

Go to the video recording of the meeting. Go to a PDF of the meeting presentation.

6/28/2022 Public Meeting Jun 28, 2022
2/2/2022 Project Meeting Information Feb 2, 2022

City staff and the project design consultant CMA Engineers shared details on the project and solicited residents’ thoughts on project requirements and opportunities. The meetings included a review of the existing site conditions, contemplated improvements, the design schedule, and a question and answer period. Future public meetings will address the proposed design approach and overall construction timeline.

Through February, the City and its subcontractors surveyed homes and buildings in the area to determine the location and elevation of sewer service pipes from each building. This review ensures that the new sewer main accommodates these outflows properly. The City is working with CMA Engineers (Portsmouth, NH) and Flow Assessment (Auburn, NH) to conduct those surveys and asks for your cooperation and assistance.

map of orchard Street revision

Project Documents

Project Video